HOPE Project
timeline - first draft



M = Month from start, Y = year from start
Web site reserved                                     M1 Y1
Web site components                               M1 Y1
Plans, goals, timeline, budget drafts        M1 Y1
Sponsor requests                                      M1 Y1- M4 Y1
Laboratory prepared to receive                M1 Y1
Fusion research                                         M1 Y1 – M3 Y1
Car housing secured                                 M1 Y1– M2 Y1
Car acquired                                              M2 Y1 – M5 Y1
Aluminum alloy research                           M1 Y1– M5 Y1
Hydrogen test runs                                     M3 Y1- M6 Y1
Gadolinium, D2O, etc acquired                M2 Y1 - M3 Y1
Specialize tools and equipment               M2 Y1 – M5 Y1
Metal research for underwater plasma    M3 Y1– M8 Y1
Plasma system improvements                 M5 Y1– M9 Y1
Solar cells researched, acquired              M6 Y1- M8 Y1
Car basic modifications                             M6 Y1– M9 Y1
Motor modified                                            M6 Y1– M9 Y1
Battery replacement                                   M8 Y1 – M11 Y1
Charging circuits                                         M8 Y1 – M12 Y1
Solar cell mounting, testing                        M6 Y1 – M12 Y1
Hydrogen generation achieved                 M8 Y1– M1 Y2
Motor worked and peaked for H2             M8 Y1– M2 Y3
Aluminum feed system                               M11 Y1 – M5 Y2
Plasma electro feed system                      M11 Y1 – M6 Y2
Integration of Al with fusion system           M11 Y1 - M6 Y2
Road trials with H2 alone                           M11 Y1 – M5 Y2
Stirling engine acquired                             M8 Y1– M2 Y2
Plasma focus heating engine                    M11 Y1 – M7 Y2
Local road trials                                           M2 Y2- M7 Y2
Redesign after/during trials                        M2 Y2– M8 Y2
Peaking Fusion system                              M7 Y2 – M11 Y2
Shipping car to departure site                   M8 Y2 -  M1 Y3
Time buffer, safety                                      M1 Y3 – M2 Y3
Event                                                            M3 Y3
Performance evaluation report                  M3 Y3 – M5 Y3
IP work if needed                                         M8 Y3 – M5 Y3
* Monthly status reports
* Weekly IP documentation during work
* Notice overlapping of tasks
* Notice some fusion research will be done through out the time.
* Attempts will be made to integrate the Aluminum/ hydrogen subsystem and the fusion subsystem. It may be possible to use the same alloy for both uses if properly chosen and prepared. 
* The Hydrogen generation materials may incorporate “trade secret items” revealed in confidential performance reports after IP is secured.
* The plasma fusion system may opt to peak production of hydrogen instead of peaking production of heat ad efficiency results are tabulated.